TOKYO – An earthquake jolted Japan on Saturday hours after the country's nuclear safety agency ordered plant operators to beef up their earthquake preparedness systems to prevent a recurrence of the nuclear crisis roiling the region north of Tokyo.
There were no immediate reports of damage from the magnitude-5.9 quake, and there was no risk of a tsunami similar to the one last month that crippled the Fukushima Dai-ichi nuclear plant, causing Japan's worst-ever nuclear plant disaster. Japan has been hit by a string of smaller quakes since the magnitude-9.0 earthquake hit the country on March 11.
On Saturday, the government reported that levels of radioactivity in seawater near the plant had risen significantly in recent days. The level of radioactive iodine-131 spiked to 6,500 times the legal limit, according to samples taken Friday, up from 1,100 times the limit the day before. Levels of cesium-134 and cesium-137 rose nearly fourfold.
The rise could have been caused by the installation Thursday of steel panels intended to contain the radiation which may have temporarily stirred up stagnant waste in the area, Hidehiko Nishiyama of the Nuclear and Industrial Safety Agency told reporters. However, the increase in iodine, which has a relatively short eight-day half life, could signal a possible new leak, he said.
"We want to determine the origin and contain the leak, but I must admit that tracking it down is difficult," he said.
The nuclear plant's operator, Tokyo Electric Power Co., also began dumping sandbags filled with zeolite, a mineral that absorbs radioactive cesium, into the sea in areas heavily contaminated with radiation in an effort to reduce danger from the leaks.
Meanwhile, the newspaper Asahi Shimbun reported, without citing its sources, that a secret plan to dismantle TEPCO was circulating within the government. The proposal calls for putting TEPCO, the world's largest private electricity company, under close government supervision before putting it into bankruptcy and thoroughly restructuring its assets. Most government offices were closed Saturday, and the report could not be immediately confirmed.
In the wake of the nuclear crisis, the government ordered 13 nuclear plant operators to check and improve outside power links to avoid earthquake-related outages that could cause safety systems to fail as they did at the Fukushima plant, Nishiyama told reporters late Friday. The operators, including TEPCO, are to report back by May 16.
Power outages during a strong aftershock on April 7 drove home the need to ensure that plants are able to continue to operate crucial cooling systems and other equipment despite earthquakes, tsunamis and other disasters, Nishiyama said.
Utility companies were ordered to reinforce the quake resistance of power lines connected to each reactor or to rebuild them. They also must store all electrical equipment in watertight structures. Earlier, the nuclear agency ordered plant operators to store at least two emergency backup generators per reactor and to install fire pumps and power supply vehicles as further precautions.
The massive 46-foot (14-meter) wave that swamped Fukushima Dai-ichi last month knocked out emergency generators meant to power cooling systems. Since then, explosions, fires and other malfunctions have compounded efforts by TEPCO to repair the plant and stem radiation leaks.
TEPCO said Saturday it had moved power sources for some of the reactors at the stricken plant to higher ground by Friday evening in order to avoid another disastrous failure in the event of a tsunami.
Goshi Hosono, an adviser to the prime minister and member of the nuclear crisis management task force, said the damaged reactors were much more stable than they had been earlier in the crisis and TEPCO was preparing to unveil a plan for restoring cooling capacity to the ailing reactors "soon."
"Problems are still piled up and we are far from the end of crisis," he told a TV news program, citing radioactive water as one of the biggest headaches. "I expect there will be more mountains that we have to climb over."
The crisis at the Fukushima plant has forced tens of thousands of people to evacuate to avoid exposure to radiation. On Friday, TEPCO announced plans for 1 million yen ($12,000) in initial compensation for each evacuated household, which it expects to cost it 50 billion yen ($600 million). As costs mount for the utility, TEPCO President Masataka Shimizu said it would consider cutting executive salaries as well as a number of its more than 52,000 employees.
Radiation leaks from the crisis have contaminated crops and left fishermen in the region unable to sell their catches, adding to the suffering of communities already devastated by earthquake and tsunami damage.